Serious nature violations at e site wherein owner constructed altogether commercial construction on ground and first floor were not highlighted in BOCA notices under Section 7(3) and 7(1) served to owner and in a way made every possible efforts to save commercial construction of owner raised after getting residential site plans approved from JMC and covering hundred percent plot area and raising both ground and first floor both measuring 1040 Sqft each against permitted 510 sqft without maintaining setbacks and any provision of public parking within premises
Owner deviating from residential approved site plan raised illegal and unauthorized construction in excess of permitted area including three shops on ground floor keeping small gate on right side to reach at first floor , raised commercial construction hall 1040 Sqft on first floor and 2nd floor commercial hall also measuring 1040 sqft without maintaining setbacks thus raising three commercial floors after getting residential site plans approved from JMC. The owner raised 2nd floor without getting site plan approved from JMC
GY CORRESPONDENT
jammu, OCT 24
JMC served a demolition notice under section 7(3) under COBO Act 1988 vide No. MJ/CEO/128/3/2018 dated 14-12-2018 to Raman Sharma s/o Lt Rameshwar Sharma on private land of village Channi Kamala , Sector-3, Ward-51Channi Himmat Housing colony falling under Khasra No. 4 Min on main road of Railway track for starting shuttering work over the existing walls on 2nd floor without permission of JMC without maintaining setbacks claiming that the said illegal construction seriously affects the planned development of Jammu city and contravenes the zoning regulation . The owner was served 5 days ultimatum to demolish violated construction failing which the same will be done at his risk and cost.
It deserves mentioning here that present owner Raman Sharma had purchased this private piece of land having existing ground floor from Avtar Singh s/o Gurcharan Singh on whose name the residential site plan was approved from JMC vide No. 1355/BS/2010 dated 25-1-2011 allowing owner ground ground floor 510 Sqft and thereafter the owner again got approved site plan vide No. 636/BS/17 dated 7-3-2018 allowing owner first floor residential 510 Sqft on existing ground floor as residential . The owner was duty bound to observe setbacks including front – 8 ft 3 inch , Rear- 5 ft for residential purpose. But the new owner Raman Sharma deviating from residential approved site plan raised illegal and unauthorized construction in excess of permitted area including three shops on ground floor keeping small gate on right side to reach at first floor raised commercial hall 1040 Sqft against permitted 510 sqft on first floor and 2nd floor commercial hall also measuring 1040 sqft covering hundred percent plot area without maintaining setbacks. The owner raised 2nd floor commercial hall without getting site plan approved from JMC.
When locals strongly objected commercial construction after getting approved residential site plan , JMC in order to save their skin served owner BOCA notice under section 7(1) vide No. JMC/CEO/128/1//2018 dated 10/12/2018 serving owner 48 hours ultimatum to reply as to why Khilafwarzi should not demolish the violated construction raised contrary to approved residential site plan.
Worthwhile to mention here that the serious nature violations at the site wherein the owner raised altogether commercial construction on ground and first floor were not highlighted in BOCA notices under Section 7(3) and 7(1) served to owner and in away made every possible efforts to save the commercial construction of owner raised after getting residential site plan approved from JMC and covering hundred percent plot area and raising both ground and first floor both measuring 1040 Sqft each against permitted 510 sqft as residential.
Anyhow JMC sealed commercial building under section 8(1) of BOCA Act 1988 vide sealing order No. JMC/CEO/29-31 dated 14-12-2018 issued by then Joint Commissioner (Adam) JMC claiming that the owner didn’t stop unauthorized commercial construction despite serving him notices under Section 7 (1), 12 (1) and 7(3) . It deserves mentioning here that JMC in the name of sealing commercial violated building sealed only small gate at ground floor to reach at first and 2nd floor. The owner meanwhile approached J&K Special Tribunal against BOCA notice 7(3) dated 14-12-2018 and got status Quo from Tribunal. The JMC filed objections before Tribunal .However Tribunal decided appeal vide File No. STJ/266/18 dated 31-8-2020 setting aside impugned order under 7(3) notice dated 14-12-2018 and directed JMC to de-seal the building.
JMC however didn’t de-seal the building and infact approached Divisional Bench of J&K High Court Jammu against Tribunal’s order dated 31-8-2020 under WP (C ) No. 2258/2021 ,CM No. 8037/2021 in case titled JMC BOCA Authority Vs Raman Sharma r/o Channi Himmat Jammu and obtained status Quo order against Tribunal’s order dated 31-8-2020 and next date of hearing fixed on 7-12-2021. Since then the case is still pending before High Court Jammu. It deserves mentioning here that the owner Raman Sharma also filed Civil Miscellaneous petition (CMP) under CM No. 7833/2023 whose next date of hearing along with main petition WP (C ) No. 2258/2021 has been fixed on 22-11-2024 wherein JMC has been given final opportunity to file objections in the case under order passed by High Court dated 9-10-2024.
It is pertinent to mention here that despite status Quo order of High Court dated 21-10-2021 in place and the trial of above mentioned case is still pending before High Court, the owner on his own from the last one week has restarted construction including making alteration and also plaster work on first floor and also constructing bathroom towards backside facing railway track without any de-sealing order and also in contempt of High Court order besides without permission from JMC by opening small gate at ground floor which was sealed . In light of above Commissioner JMC should personally intervene as contempt of High Court orders is serious nature offence and whosoever is responsible for dereliction of duty from JMC side should be punished as per established rules and norms under law.
Trending
- JMC allows functioning of Axis Bank branch from violated two floor building when trial under BOCA notices 7 (1) & 7 (3) still going on at private land falling under Khasra No. 140/2 Min, Sector-3, Ward-51 Channi Himmat Housing Board colony without JMC NOC and without parking facility within premises
- JMC unaware of fresh construction/alteration on private land in Sector-3, Ward-51 Channi Himmat falling under Khasra No. 4 Min owned by Raman Sharma despite status Quo in place and sealing order intact and when trial of case still going on in High Court of Jammu and next date of hearing is on 22-11-2024
- JMC fails to stop ongoing construction of three unauthorized shops at bifurcated residential plot 29-C Shastri Nagar Housing Board Colony Ward-23 without approval of site plan from JMC despite letter by Dy General Manager Housing Board Unit-II, Jammu dated 18-10-2024 to Joint Commissioner ,JMC to stop ongoing unauthorized construction of three shops after lapse of residential approved site plan dated 26-11-2018 making land use change from residential to commercial
- JMC openly facilitating land use change from residential houses into commercial on private properties in Sector-3, Ward-51 falling under Khasra No. 427 Min owned by Rajinder Sharma, Lt Sunil Sharma and Kala Mahajan without parking facility , JMC permission against JMP-2032, Unified Building Bye-laws 2021 making mockery of JMC Act 2000
- Dy Commissioner South and Enforcement Officer, JMC no follow-up action after J&K Special Tribunal Bench-III order dated 12-1-2023 set-aside BOCA demolition notice under Section 7(3) dated 8-7-2022 served by Joint Commissioner(R&E) without being vested with powers to serve notice to owner of residential plot 584/4, Channi Himmat ,Ward-50 but not violations in notice and directing JMC at liberty to take fresh action as per mandate of law but same still awaited even after lapse of 22 months and serious violations at Ground plus two floors besides illegal shop still intact at site and illegal activity going on from residential house making land use change as JMC stopped proceedings against owner
- Despite Tribunal decision that Status Quo granted by Tribunal dated 15-9-2021 at residential site 9/6 Channi Himmat Ward-50 will remain in operation with liberty granted to JMC `Commissioner to exercise power vested in him to require alteration of work in order to bring the structure in conformity with building permission under section 256 of JMC Act 2000 afresh didn’t initiate any fresh proceedings even after three months of decision as a result of which violations of 2273 sqft remained intact and owner started residing in premises when status Quo order is still in operation
- JMC Enforcement staff fails to stop open and brazen conversion of ground floor residential into full-fledged commercial Hall at corner residential plot 274/3 Channi Himmat Housing Board colony in Ward 50 on main road side of Colony already running unauthorized commercial shop and running Atulya Laboratory and Lovely Medicos and Lab on ground floor of his residential house
- JKRERA, JMC failed to take cognizance of ongoing construction of commercial flats after clubbing four differently approved residential site plans on private land falling under Khasra No. 346 and 347 Min, Sector-2, Ward-51 Channi Himmat in residential area without maintaining setbacks and against JMP-2032 and Unified Building Bye-laws 2021