It is surprising to note that when JMC didn’t provide any permission for residential construction how owner managed to raise ground floor without maintaining setbacks and why JMC so far JMC hasn’t served any BOCA notices to owner, why Enforcement Inspector deputed in ward-50 not taken to task for not reporting construction without JMC permission
JMC should remember that J&K Development Act, 1970 vide Section 13 clearly provides that no person including the department of the govt shall undertake or carry out development of any land or building in any zone unless permission for such development has been obtained in writing from the authority in accordance with the provisions of the Act.
Enforcement Inspectors don’t maintain proper registers of each ward and take action against violators as admissible under rules with proper entry on action taken report register. When Enforcement staff is informed by locals about violated construction they often say that they will visit the site and will look into but if they maintain register the violations should be at finger tips for immediate action.
Enforcement Inspectors don’t submit action taken report to concerned I/c EO/AEO for its onward submission to Secretary /Dy Commissioner (North) for action under rules as per relevant provision of law in vogue. As a result of which I/c EO/AEO don’t get action reports confirmed or counter checked by Secretary /Dy Commissioner (North) on weekly basis
GY CORRESPONDENT
jammu, sep 7
BB Sharma s/o Maya Ram r/o 585 Lakshmi Nagar, Sarwal Jammu allotted a residential plot 66/6 measuring 50×100 (5000 Sqft) in Channi Himmat Jammu without getting site plan approved from JMC started residential construction in the month of April 2023 with the help of then Enforcement Inspector in Ward 50 Jasbir Singh and constructed ground floor without maintaining any of setbacks as mandatory in case of residential construction and covered nearly 80% of plot area when he was allowed only 45 % construction as per JMP-2032 and Unified Building Bye-laws 2021.
This was authenticated by Senior Town Planner JMC while replying to an RTI application dated 27-5-2023 vide letter No. JMC/BS/RTI/91-93 dated 20-6-2023 filed in this regard by replying that no building permission has been granted in favour of BB Sharma s/o Maya Ram r/o 585 Lakshmi Nagar, Sarwal Jammu owner of 66/6 measuring 50×100 (5000 Sqft) in Channi Himmat Jammu .
It is surprising to note that when JMC didn’t provide any permission for residential construction how owner managed to raise ground floor without maintaining setbacks and more surprising is to note that JMC so far hasn’t served any BOCA notices to owner. The J&K Development Act, 1970 provides for the constitution of development authorities for any local area as body corporate and provides for the preparation of Master Plan 2032 and Zonal Plans, the development of the area is supposed to take place in accordance with the said plans .
The Act vide Section 13 clearly provides that no person including the department of the govt shall undertake or carry out development of any land or building in any zone unless permission for such development has been obtained in writing from the authority in accordance with the provisions of the Act.
But sadly JMC didn’t take serious cognizance of above mentioned provisions and allowed owner to raise violated ground floor without maintaining setbacks and site plan approval from JMC. Fully encouraged and supported by JMC enforcement staff deputed in the area , the owner has started construction of first floor from the last week and meantime the plaster work of ground floor is going on as the newly deputed Enforcement Inspector Ram Khajuria dated 24-7-2023 is well known for entertaining such constructions and his transfers have been mainly due to crossing limits of allowing violated constructions in his wards.
Secretary JMC while replying to RTI application vide her letter No. JMC/CEO/S/179-80 dated 29-8-2023 in this regard has replied that as per record of JMC ,no violation report has been submitted by concerned Enforcement Inspector in Ward-50 about construction going on at 66/6 Channi Himmat Jammu which only means that JMC enforcement has definitely helped owner by not timely reporting violative construction at the initial stage of violation and as a result of which the construction of first floor has been started from the last week.
Most of the Enforcement Inspectors deputed in 75 Wards don’t perform their duties honestly, for example the first condition that the Enforcement Inspectors and I/C Enforcement Inspectors shall conduct extensive checking in the allotted wards and make proper detailed list of ongoing constructions in their respective area of jurisdiction. Had it been so, no one would have dared to undertake unauthorized constructions in Zonal planned colonies and precious time of J&K Special Tribunal and RTI Activists would have been saved.
The condition 2 states that they shall maintain proper registers of each ward and take action against violators as admissible under rules with proper entry on action taken report register. But surprisingly when Enforcement staff is informed by locals about violated construction they often say that they will visit the site and will look into but if they maintain register the violations should be at finger tips for immediate action.
Under condition3, in reality they don’t submit action taken report to concerned I/c EO/AEO for its onward submission to Secretary /Dy Commissioner (North) for action under rules as per relevant provision of law in vogue. As a result of which I/c EO/AEO don’t get action reports confirmed or counter checked by Secretary /Dy Commissioner (North) on weekly basis . In light of above ,the need of the hour is to make necessary reforms in functioning of JMC otherwise the way JMC is functioning presently it will prove disastrous for JMP-2032 and Unified Building Bye-laws 2021 also.
Commissioner JMC should take serious cognizance of this as on one hand JMC claims simplifying procedure for applying building permissions and if even then the owner like BB Sharma doesn’t take permission from JMC and successfully completes ground floor without maintain setbacks and covering 80% plot area without being served BOCA notices under relevant sections of BOCA Act should hold Enforcement staff responsible for remaining silent and not reporting violations at initial stage otherwise the whole functioning of JMC would be collapsed very soon.
Trending
- JMC enforcement staff after shaking hands with owner allows restart of three unauthorized big size commercial shops at residential plot 29-C, Shastri Nagar, Ward-22 on 19-2-2025 which remained stopped for sometime after aggrieved locals opposed commercial construction and print media highlighted violated construction along with pictures making land use change without getting site plan approved from JMC which can’t be done plot being bifurcated
- Residents of Channi Himmat strongly resent Commissioner JMC seeking NOC from J&K Housing Board to establish Rehri Zone at existing Parking site of Channi Himmat main Shamshan Ghat constructed at estimated cost of Rs 78 lacs over Thangar Nallah drain urging both JMC and Housing Board to drop idea in larger interests of Channi Himmat residents and those attend cremations
- JMC finally serves sealing order under JMC Act 2000 to owner of private land falling under Khasra No. 477 Min in Sector-3, Ward-51,old village Channi Himmat when four floors violated structure making 66.37% violations on each floor already completed and husband of owner Dr Rajeev started running Day Care Medical Centre by covering 750 Sqft against owned 644 Sqft without maintaining setbacks and public parking within premises against JMP-2032 and Unified Building Bye-laws 2021
- Forest fire rages on at shrine board from last one month, no accountability
- JMC’s sealing & de-sealing orders to owner of residential plot 274/3,Ward-50, Channi Himmat proved counter-productive for owner as full-fledged commercial hall after removing partition walls of existing ground floor still intact despite undertaking submitted by owner to construct brick walls partition but constructing plywood partitions to hoodwink JMC authorities
- JMC serves owner eyewash de-sealing order without mentioning actual violations to owner of residential plot 328/4 , Ward-50 Channi Himmat for raising violated full-fledged commercial ground floor plus three floors against permitted ground plus two floors without maintaining setbacks, height against JMP-2032 and Unified Building Bye-laws 2021 when construction going on from last ten months and now reaches finishing level
- JMC approves commercial site plan allowing owner to cover 100% plot area in construction of commercial basement for storage & utility and commercial ground floor without mentioning their height not mandating to maintain setbacks at JDA’s commercial site No.5 Phase-II commercial complex Fruit Market, Narwal Fruit Mandi Jammu, Ward-49 adjoining with Head Branch of J&K Grameen Bank against JMP-2032/Unified Building Bye-laws 2021
- JMC unmoved towards unauthorized running of children play centre in both first and 2nd floors and a restaurant cum canteen in the third floor of residential plot 649/3 on main road of Channi Himmat Housing Board Colony even when J&K Housing Board endorsed three letters to Commissioner JMC to act against owner for running commercial activities from residential plot by making sheer breach of lease deed and also against JMP-2032 and Unified Building Bye-laws 2021