The owner deviating from approved site plan raised commercial hall without maintaining setbacks and didn’t construct proper kitchen, living room, drawing room and porch. However it deserves mentioning here that the owner initially to hoodwink general public kept window for kitchen on ground floor and main entry from porch area and raised stairs quite back of porch to reach first and 2nd floors and didn’t construct duplex house and keeping entry to kitchen from porch area . The owner actually constructed commercial hall measuring nearly 1400 sqft area against allowed 1056 sqft each floor besides constructing extra room on 2nd floor excluding mumty
GY CORRESPONDENT
jammu, nov 12
One Surinder Kour wife of Charan Singh r/o Tali Morh, Miran Sahib Jammu purchased a residential plot 328/4 measuring 30×55 (1650 Sqft) on main 60 ft road of Channi Himmat colony in Ward-50 from original allottee Tilak Rj Gupta for residential purposes. The owner accordingly got approved residential site plan from JMC vide No. 148/JMC/BS/2023-24 dated 25-4-2023. As per approved site plan, the owner was allowed ground+ two floors measuring 98.16( 1056 Sqft) each floor. The owner was duty bound to observe mandatory setbacks including front- 3.96 mtr (13 ft) and rear -2 mtr(6.5 ft). The height of building was fixed as 10 mtr from the front road level. The owner accordingly paid residential building fee Rs 15707. As per drawing of approved site plan , the owner towards front side was to construct kitchen left side ,porch right side, followed by living room drawing room then back of them two bed rooms with common toilet along with stairs inside as witnessed in duplex residential house. On first and 2nd floor, the owner was allowed verandah on porch area and rest of construction altogether same as in case of ground floor.
The owner deviating from approved site plan raised violated construction without maintaining setbacks and didn’t construction proper kitchen, living room, drawing room and infact raised commercial hall. However it deserves mentioning here that the owner initially to hoodwink general public kept window for kitchen on ground floor and main entry from porch area and raised stairs quite back of porch to reach first and 2nd floors and didn’t construct duplex house by not constructing stairs alongside living room to reach first and 2nd floors and kept stairs from backside towards back of porch area . The owner actually constructed commercial hall measuring nearly 1400 sqft covering construction area of kitchen by removing exiting window and kept provision for fitting of iron shutter measuring 10×10 ft and divided porch area into a shop measuring 10×10 and separate entry to reach at first and 2nd floor as there was no indication of residential construction in absence of living room, drawing room, bed room except toilet on ground floor. The owner didn’t observe mandatory setbacks as owner left 6 ft from front side when he was supposed to leave 13 ft besides extending 3 ft galleries on three floors. Meanwhile owner successfully managed to raise two more floors at par with ground floor in area. When enforcement staff failed to stop ongoing unauthorized construction, a RTI was filed dated 28-6-2023 seeking action by enforcement staff against owner, then Secretary JMC replied that as per JMC record, no violation report has been submitted against owner in their replies dated 12-8-2023 and 21-10-2023 by concerned Enforcement Inspector deployed in Ward-50. This means that enforcement staff was in favour of owner from day one of construction and that is why they didn’t report violations at the residential site.The owner also raised extra construction of room on 2nd floor other than mumty. The owner has already completed plaster work on three floors from back and either side of building except front side.
Worthwhile to mention here that owner instead of plaster work from front side , infact started converting residential ground floor into full-fledged commercial hall by removing window of kitchen on 9-11-2024 and closed the entry to kitchen from porch by removing door and infact constructed shop measuring 10×10 ft . The owner is also using porch area measuring 10×10 ft to construct shop with separate wall and keeping altogether separate entry to reach at first and 2nd floor by cutting area of porch area by nearly 5 ft. The pictures of ongoing construction clicked on 12-11-2024 at 12 noon also indicated that ground floor construction is absolutely contrary to approved site plan and in no way it is residential construction.
It is highly unfortunate that open land use change is going on but as on date JMC enforcement staff deployed in Ward -50 including Enforcement Inspector Varun Kesar and Enforcement Officer Anil Kashyap have not moved even an inch despite bringing the same into kind notice of Enforcement staff much to the agony of aggrieved locals who have already strongly resented land use change openly and brazenly. Housing Board should also take serious cognizance of this violated construction as ongoing construction on ground floor is sheer breach of Lease deed agreement. Commissioner JMC should pay instant heed to ongoing unauthorized constructions and ask enforcement staff to perform their duty honestly and sincerely failing which it would be extremely difficult to implement JMP-2032 in letter and spirit.
Trending
- Commercial construction reaches third floor on residential plot 250-C, Sector-2 Channi Himmat Zonal planned colony without maintaining setbacks completely contrary to residential approved site plan with no provision of windows, ventilators, cut out and JMC now serves owner notice under provision of section 253(1) JMC Act 2000 without mentioning actual violations like three floors commercial, extended galleries, iron stairs from backside and no internal walls partitions
- JMC stuns Channi Himmat by sealing Varmani Shopping Complex, Channi Himmat, Sector-2, Ward-50 on 30-12-2024 for violations to tune of 8053 sqft in basement+ground+3 floor excluding violated 4th floor of 2674 sqft correcting earlier violations of 1704 sqft and de-sealing Complex on 31-12-2024 for 20 days besides allowing its functioning since 2013 without depositing compounding fee Rs 127800 by owner as decided by J&K Special Tribunal dated 30-12-2013
- JMC enforcement staff after shaking hands with owner allows restart of three unauthorized big size commercial shops at residential plot 29-C, Shastri Nagar, Ward-22 which remained stopped for sometime after aggrieved locals opposed commercial construction and print media highlighted violated construction along with pictures dated 21-10-2024 making land use change without getting site plan approved from JMC which can’t be done plot being bifurcated
- JMC yet again makes mockery of notice under section 253 (1) JMC Act 2000 served to owner of residential plot 66/5 ,Ward-50 Channi Himmat wherein serves 48 hours ultimatum to owner to remove violations dated 14-10-2024 but without taking follow-up action against owner approves fresh site plan dated 28-11-2024 when existing violations were not removed by owner after giving written undertaking and further construction of two floors started
- JMC Building Section out of way sanctions stilt floor commercial parking stage-1st at commercial sites 3,4 and 5 in Sector-2 Ward-50 Channi Himmat and enforcement staff fails to take action against owners when differently approved site plans clubbed and raised joint construction of commercial halls as single unit without maintaining setbacks and not constructing new stilt floors commercial and in spite of violations in stage-1st construction JMC approved stage 2nd construction and at present stage-2nd construction going on from last 15 days with help of enforcement staff
- Commercial construction reaches third floor on residential plot 250-C, Sector-2 Channi Himmat Zonal planned colony without maintaining setbacks completely contrary to residential approved site plan with no provision of windows, ventilators, cut out but JMC yet to take action against owner despite highlighting violated construction in Print Media along with pictures and bringing same in notice of concerned enforcement staff deployed in Channi Himmat Zonal planned colony
- JMC Enforcement staff deputed in Channi Himmat Ward-50 allowing construction of commercial hall on residential plot 634/3 without maintaining setbacks, without partition of walls, windows, ventilators with stairs on front side and also with lift provision absolutely contrary to residential approved site plan doing huge injustice with those who have purchased commercial sites
- Existing violated structure on private land falling under Khasra No. 4 Min, Ward-51, Channi Himmat earlier sealed, site plan withdrawn, then restored without removing violations now undergoing complete renovation and conversion from sanctioned mixed use of both residential and commercial to full-fledged commercial halls on three floors measuring 10000 sqft each to run big size shopping mall without JMC permission but with help of enforcement staff deployed in Channi Himmat